Social and Environmental Standards procedure

1.0

Step

Conduct Social and Environmental Screening to identify potential social and environmental risks, including dispute risks.

Responsible Party

Project Developer and/or Portfolio Developer

Template/Guideline
Explanatory Notes

SES Toolkit

Guidance Note: UNDP Social and Environmental Standards (SES)

Stakeholder Response Mechanism (SRM) Guidance

Identify and plan management actions to address significant risks, including dispute risks, and to build or support national risk management capacities, and integrate into Project Document.

Include results of SESP as an Annex to the Project Document.

Enter identified risks, including dispute risks, and management measures into Project Risk Register.

2.0

Step

Implement identified management actions and track in Project Risk Register.

If grievances are received through the Stakeholder Response Mechanism (SRM), manage and resolve requests using process outlined in SRM Guidance.

Responsible Party

Project Manager

Template/Guideline
Explanatory Notes

Stakeholder Response Mechanism (SRM) Guidance

SES Toolkit

Assess ongoing compliance with the Social and Environmental Standards as part of ongoing quality assurance and risk reporting.
 

 

Update SESP and risk categorization if there is a substantive revision to the project or if the context has changed in a way that alters the risk profile of the project.
 

3.0

Step

Review social and environmental and risk prevention and management experience; note lessons learned and opportunities for improvement in project closure/evaluation.

Responsible Party

Project Manager

Template/Guideline
Explanatory Notes

 

Stakeholder Response Mechanism (SRM) Guidance

SES Toolkit

 

Formulate Programmes

1.0

Step

Contribute to the roadmap for an inclusive CCA and Cooperation Framework. 

Responsible Party
Template/Guideline
Explanatory Notes

UNSDG | Consolidated Annexes to the Cooperation Framework Guidance  

In transition settings, the UN country team must consult with the integrated mission task force or integrated task force to ensure coordination.

A roadmap is not required for regional and global programmes.

Involve the Regional Directors team and regional peer support groups as early and frequently as possible. 

1.1

Step

Once final, send the roadmap to all national partners, and to the Regional Directors team, peer support group, headquarters of all UN agencies and the United Nations Development Operations Coordination Office.

Responsible Party

Resident Coordinator

Template/Guideline
Explanatory Notes

This enables headquarters to position itself to support as appropriate.

2.0

Step

Prepare a quality analysis for the programme and contribute to the CCA as relevant.

Responsible Party
Template/Guideline
Explanatory Notes

UNSDG CCA guidance  

The analysis must provide inputs to the theory of change and define the UN's programming priorities, including UNDP's comparative advantage in the programming and larger financing context.

2.1

Step

Forward the integrated UN country team analysis to the regional peer support group mechanism for quality support and assurance.

Responsible Party
Template/Guideline
Explanatory Notes

UNSDG | Consolidated Annexes to the Cooperation Framework Guidance 

3.0

Step

Complete the country level macro-assessment of HACT.

Responsible Party
Template/Guideline
Explanatory Notes

UNSDG HACT Guidelines

Discuss arrangements for audit of government expenditures with the government development coordination authority as per the HACT framework.

4.0

Step

Develop inputs for the Corporate Framework theory of change.

Responsible Party
Template/Guideline
Explanatory Notes

Cooperation Framework Theory of Change Guidance 

A strategic prioritization exercise involving UN system entities and stakeholders should be led by the government to link the comparative advantages of the UN system to national development priorities.

UNDP's inputs to the theory of change should be developed in a participatory and evidence-based manner, identifying areas where the organization has a comparative advantage and potential to mobilize funding, based on evidence from evaluation and lessons learned.

5.0

Step

Contribute to the Cooperation Framework, attach the legal annex to the signed Cooperation Framework. 

Responsible Party
Template/Guideline
Explanatory Notes

Cooperation Framework Guidance

  • Following the strategic prioritization exercise, agree on a set of outcomes to support national development priorities. Prepare a SMART results matrix based on the country analysis.
  • If the Cooperation Framework will replace the CPD, a UNDP-specific country programme results matrix must be attached.

Country programmes will be assessed against UNDP quality standards.

*IMPORTANT: For individual project documents to be approved without signature of the government's development coordination authority, the Cooperation Framework legal annex must specify that all forms of assistance provided by UNDP further to the Cooperation Framework will be covered by the applicable standard basic assistance agreement (SBAA or predecessor agreement plus supplementary legal annex). The Legal Office must clear the text to confirm that it meets the requirements to consider the Cooperation Framework in lieu of a signed project document.

5.0 ALT 1

Step

If the legal annex is not attached to a signed Cooperation Framework or if there is no signed Cooperation Framework with a government, prepare and sign a country programme action plan with the government.

Responsible Party
Template/Guideline
Explanatory Notes

5.0 ALT 2

Step

If there is no recognized government able to sign the country programme, seek approval from the Associate Administrator through the Bureau for Policy and Programme Support/Effectiveness Group for direct execution of the programme based on the country programme document.

Responsible Party
Template/Guideline
Explanatory Notes

This establishes a lack of a recognized national government that can accept national ownership of the programme; UNDP assumes the risks of directly executed programmes (DEX).

6.0

Step

Develop a country programme document that adheres to the quality standards.

Responsible Party
Template/Guideline
Explanatory Notes

The CPD can specify up to four Cooperation Framework outcomes to which UNDP contributes.

It must include indicative outputs consistent with the theory of change, and prospective UNDP and partner financial resources.

Consider using the RBM Guidance to assist in developing the CPD in 10 steps.

6.0 ALT 1

Step

Develop the regional programme document.

Responsible Party

Programme manager/ Regional Bureau Director

Template/Guideline
Explanatory Notes

6.1

Step

Prepare a costed evaluation plan with sufficient programme coverage, consistent with the Cooperation Framework evaluation plan if relevant.

Responsible Party
Template/Guideline
Explanatory Notes

UNDP Evaluation Guidelines

6.2

Step

Ensure the programme budget is realistic and reflects an efficient use of resources.

Responsible Party
Template/Guideline

RMT

Explanatory Notes

UNSDG guidance

6.3

Step

Ensure incorporation of the PCAP into programme design. 

Responsible Party
Template/Guideline
Explanatory Notes

The RM Toolkit and Communications Toolkits contain guidance with the required elements and a suggested format for the Partnerships and Communication Strategy and Action Plan (PCAP).

Consider using the RBM Guidance to assist in developing the PCAP.

7.0

Step

In high-risk security settings, contribute to the UN-wide programme criticality assessment to determine acceptable security risk levels for UN personnel in the required frequency.

Responsible Party
Template/Guideline
Explanatory Notes

In a prolonged crisis with elevated security risk, a UN programme criticality assessment is required to determine acceptable risk levels for different outputs, and to indicate where additional security risk management measures or alternative delivery modalities would be required.

8.0

Step

Participate in joint results groups and associated joint workplans, if applicable.

Responsible Party
Template/Guideline
Explanatory Notes

UNSDG | Guidance Note on a New Generation of Joint Programmes

Formulate Development Projects

1.0

Step

Identify pipeline concept and mobilize partners.

Responsible Party

UNDP Programme Officer

Template/Guideline
Explanatory Notes

Identify new pipeline concepts by analysing gaps in the programme’s theory of change that are not already being addressed. 

Funding and collaborating partners and potential stakeholders must be identified and consulted as early as feasible, ensuring a wide range of partners (international financial institutions, civil society, private sector, etc.)

A concept note may be helpful to articulate ideas for particularly complex projects or to obtain early support from partners. The proposed content can include: output(s) and linkage to CP outcome(s); approach, method and capacity development strategies; stakeholder analysis; potential implementing partner; potential main financing partner(s); and indicative funding requirements. 

For GCF projects a Concept Note is required, and for GEF Projects this concept note is called a PIF.

Create a new pipeline linked to the programme and Strategic Plan in the corporate planning system. If a new programme output will be needed to respond to the development need, make a note to discuss in the next Programme Steering Committee meeting.

System action points:

Create a project proposal in the corporate planning system, generating a project number with one or more linked outputs; link the proposal to the programme tree (country programme document output).  

*If the project is part of a portfolio, it will share the project number with other projects in the portfolio. A project budget is reflected in one or more output IDs. An output ID can only reflect the budget from one project with one implementing partner.

*If a decision is taken not to continue with the proposal, record this decision in the corporate planning system to close the proposal. 

1.1 ALT

Step

For Environmental and Climate Vertical Fund Projects (those supported by the GEF, GCF, Adaptation Fund and other vertical funds), conduct an initial screening and assessment to determine if the conditions and criteria for accepting government requests for programming are met. 

Responsible Party

Project Manager

Template/Guideline
Explanatory Notes

Note that additional quality assurance must be provided by the BPPS/Vertical Fund Hub for GEF and GCF projects as outlined in the RACI.

2.0

Step

Appoint a developer to formulate the project

 

Responsible Party
Template/Guideline
Explanatory Notes

2.1

Step

If an implementing partner needs to be selected prior to developing the project document, see Select Implementing Partners

Otherwise, select an implementing partner at the appropriate time
 

Responsible Party

UNDP Programme Officer

Template/Guideline
Explanatory Notes

2.2 OPT

Step

Develop initiation plan (if applicable)

Responsible Party

UNDP Programme Officer

Template/Guideline
Explanatory Notes

For GEF Project Preparation Grant (PPG) projects, the signed PPG Delegation of Authority (DOA), including the annexed PPG Total Budget Workplan, constitutes the equivalent of the corporate Project Initiation Plan for the PPG phase, serving as the formal authorization for initiating PPG activities. The same process is followed for Adaptation Fund Project Formulation Grant (PFG) projects.

3.0

Step

Develop a project document that adheres to UNDP quality standards and partner requirements

Responsible Party

UNDP Programme Officer

Template/Guideline
Explanatory Notes

The project/portfolio document should attach:

  • The SESP and any related assessments and management plans
  • Detailed terms of reference for key project positions and the project board
  • Standard agreements such as the project cooperation agreement when a civil society organization is implementing and cost-sharing agreements
  • Standard letter of agreement between the implementing partner and responsible parties for the implementation of the project
  • Procurement plan
  • Project monitoring schedule plan
  • List of foreseeable knowledge products, if relevant

For further guidance, see: Results-Based Management (RBM) Hub

Consider using the RBM Guidance to assist in developing the project document in 10 steps.

3.0 ALT

Step

For joint programmes with other UN agencies, a joint programme project document should be used.

For multi-donor trust funds, each has its own project template which is approved by a steering committee and included in an operations manual.

If UNDP is requested to be the administrative agent, contact the Multi-Partner Trust Fund Office: executivecoordinator.mptfo@undp.org 
 

Responsible Party

UNDP Programme Officer

Template/Guideline
Explanatory Notes

UNSDG | Guidance Note on a New Generation of Joint Programmes
 

3.1

Step

Ensure a wide range of stakeholders participate in the formulation of the project
 

Responsible Party

UNDP Programme Officer

Template/Guideline
Explanatory Notes

Stakeholders include any parties with an interest in the project, including target beneficiary groups, civil society organizations, governments, the media, UN agencies and donors.
 
The participation of women and disadvantaged groups should be ensured throughout the project cycle, as appropriate.
 
The participation of stakeholders ensures that potential opportunities and analysis, including lessons drawn from experience, are taken into account in project design.
 
Participation promotes ownership, sustainability and commitment, without which the results are unlikely to be lasting.
 
Ensuring participation requires time and resources; adequate provision should be made for these.

Consider using the RBM Guidance to assist with steps for collaborating with all stakeholders in project formulation.
 

3.2

Step

Prepare fully costed project budgets to ensure that all anticipated programmatic and operational costs, including development effectiveness and implementation support arrangements are identified, fully costed in the budget.

 

Responsible Party

UNDP Programme Officer

Template/Guideline
Explanatory Notes

The requirements for developing a project budget are outlined in Prepare Fully Costed Budgets for Projects.
 
Refer to the detailed procedures for Costing and Budgeting of projects funded by the following partners:
 

3.3

Step

Identify potential risks, and conduct further assessment and management plans as needed in a participatory manner


 

Responsible Party

UNDP Programme Officer

Template/Guideline
Explanatory Notes

The initial project Risk Register and SESP are submitted to the project appraisal committee as annexes to the project document and recorded in the Quantum Project Results and Project Closure Workbench.

Enterprise Risk Management Policy


Managing Risks Across UNDP Programming and Operations: Guidance Note 

 

3.3 ALT

Step

Complete a risk assessment, including applying mitigatory measures, if UNDP plans to engage with the non-UN security sector. 

 

Responsible Party

Project Developer and/or Portfolio Developer

Template/Guideline
Explanatory Notes

Refer to: Human Rights Due Diligence Policy on United Nations support to non-United Nations Security Forces (HRDDP) 

3.4

Step

If the project is part of a portfolio, link the project with the portfolio number in Quantum.

 

Responsible Party
Template/Guideline
Explanatory Notes

Close and Transition (Projects)

1.0

Step

​Prepare final project review report.

Responsible Party

Project Manager

Template/Guideline
Explanatory Notes

Final project review report template forthcoming.

The report should be generated directly from the corporate planning system.

Consider using the RBM Guidance to improve the closing of projects.

2.0

Step

If required, commission final project evaluation, prepare a management response, and share findings and recommendations for learning.

Responsible Party
Template/Guideline
Explanatory Notes

Templates for this step:

Projects are required to be evaluated if they are included in the programme's evaluation plan, or if required by partners (see UNDP Evaluation Guidelines). The programme manager may request the project manager to support the commissioning, management and use of evaluation, including the preparation of a management response and implementation of committed actions.

Mid-Term/Interim and Terminal Evaluations of Environmental Vertical Fund financed projects must meet both UNDP and the relevant vertical fund requirements.

For GEF financed projects, see guidance on conducting a Terminal Evaluation and guidance on conducting a mid-term evaluation. These documents are accessible on the UNDP Independent Evaluation Office website in Spanish, French, and English (click on the GEF Project Evaluation tab). For evaluations of GCF and AF financed projects, please consult the Nature, Climate and Energy team. 

The RACI matrix sets out the roles and accountability for this stage of GEF-financed projects.

Management responses for all evaluations are required. Progress made in committed actions should be tracked in the UNDP Evaluation Resource Centre

3.0

Step

Conduct a final project review, including the final report, project closure quality assessment and project closure budget.

Responsible Party
Template/Guideline

Project status is changed from Ongoing (O) to (C) = Operationally closed

Project QA - Closure (Quantum+)
Explanatory Notes

The project board assures that all project deliverables have been produced satisfactorily and endorses the final project review report, including lessons learned.

The project quality assurance assessment (closure stage) is prepared and reviewed during the final project review. Lessons are captured during this process. See Quality Standards for Programming.

Project QA - Closure User Guide (Quantum+)

4.0

Step

Transfer or dispose of project assets and files.

Responsible Party
Template/Guideline
Explanatory Notes

Project assets and documents should be transferred to national beneficiaries or national representatives. Worthless assets are discarded. See Transfer or Disposal of Assets.

4.1 ALT

Step

Transfer by donation project assets to another UNDP project.

Responsible Party
Template/Guideline
Explanatory Notes

Guidance on donations from third parties
 

5.0

Step

Prepare and submit final financial report to UNDP.

Responsible Party

Project Manager

Template/Guideline
Explanatory Notes

Under HACT, national institutions and non-governmental organizations serving as implementing partners prepare the final FACE form. For detailed procedures, see Direct Cash Transfers and Reimbursements.

UN agencies undertaking activities under national implementation report expenditures with a project delivery report.

6.0

Step

Complete project closure activities.

Responsible Party

UNDP Programme Officer

Template/Guideline
Explanatory Notes

A check of the output financials (cash funds and allocation funds) must be done at this stage to ensure these are consistent with the funding sources for the project. This will catch issues such as miscoding funds, donors, etc. that need correction. The project should close with zero balance in the balance sheet and zero fund balance.

6.1

Step

Special donor requirements for refunds.

Responsible Party

Project Manager

Template/Guideline
Explanatory Notes

Any financial resources remaining after reconciling the project should be either refunded to the donor or transferred to general resources in line with relevant policies and procedures. Any pending refund to donors should be moved to account 21030 to avoid delays in closing the project.

Some donors, such as Belgium, the Netherlands and the United States (United States Agency for International Development, United States Department of State through a letter of credit), European Commission, Multi-Partner Trust Fund Office and trust funds, follow the special donor procedures outlined in the policy Refunds to Donors. For some donors, such as the Netherlands, projects must not be reopened once financially closed. For other donors, UNDP issues refunds as the last step before designating a project as financially closed in Quantum.

6.2

Step

Manage exceptions (i.e., outstanding advances under national implementation, signing a Combined Delivery Report, etc.

Responsible Party

UNDP Programme Officer

Template/Guideline
Explanatory Notes

Where exceptions in the project completion checklist apply, the business unit must exercise due diligence by exploring possible solutions in consultation with the implementing partner, Regional Bureau and the Bureau for Management Services/Office of Financial Resources Management. These exceptions must be handled on a case-by-case basis with approval from respective divisions in headquarters on issues outside of corporate policies and procedures. Actions taken should be documented. Offices should not move unspent balances to account 21030 for pending refunds to donors before the appropriate steps and due diligence are carried out while adopting the alternative procedures and before confirming bank account details with the donor. More information on managing exceptions can be found in Project Closure Guidelines (see section 8.0).

7.0

Step

Review and sign final Combined Delivery Report.

Responsible Party

Programme manager/Resident Representative,Implementing partner

Template/Guideline
Explanatory Notes

Under HACT, all financial transactions (FACE) are recorded in Quantum to generate the final Combined Delivery Report.

UNDP prepares the report and submits it to the project board for virtual review. It is then signed by UNDP and the implementing partner, confirming final project financial accounts and expenditures.
 

8.0

Step

Close the project.

Responsible Party
Template/Guideline
Explanatory Notes

A project is closed when all financial transactions have been reported and certified, and all project accounts are closed. The programme manager/RR is accountable for ensuring that the project is closed in accordance with the approved closure plan submitted to the project board. This must be done at the latest within 12 months of operational closure.

Quantum Actions: Forthcoming 

9.0

Step

Oversee project closure.

Responsible Party

Regional Bureau (programme QA Approver)

Template/Guideline
Explanatory Notes

The Regional Bureau is accountable for overseeing project financial closure to ensure it is completed at the latest within 12 months of operational closure.

Facts Anterior

1

Step

Submission of the request for termination of appointment. 

Responsible Party

Bureau or Country Office

Template/Guideline
Explanatory Notes

2

Step

Review of the request. 
 

 

 

Responsible Party

OHR Business Partner and Legal Office

Template/Guideline
Explanatory Notes

Review by Legal Office required in all cases. 
 

 

3

Step

Approval of the request in section 1.0.

Responsible Party

Assistant Administrator and Director, BMS

Template/Guideline
Explanatory Notes

Approve termination of appointment. 
 

 

4

Step

Implementation of the decision. 


 

Responsible Party

OHR Business Partner,

Staff member

Template/Guideline
Explanatory Notes

Notify staff member and prepare Request for Personnel Action.

Receive notification.

Calculation of indemnities.

Implement termination decision.
 

 

 

Quality Assurance (Portfolios and Development Projects)

1.0

Step

Conduct a design stage portfolio or project QA Assessment, including identifying management actions to address any areas that need improvement.

Responsible Party

QA Assessor

Template/Guideline
Explanatory Notes

Portfolio/Project QA Design and Appraisal User Guide (Quantum+)

The QA Assessor is accountable for project assurance, which is independent of the portfolio or project manager. A UNDP programme or monitoring and evaluation officer typically holds the project assurance role on behalf of UNDP. For GEF- and GCF-financed projects, project assurance is undertaken as per the requirements of the vertical funds, and these services are covered by the fee provided by the vertical fund.
Programme officer and or the M&E focal point fill the Evaluation Resource Center’s evaluation plan upon approval of the Project Document by the LPAC

1.1

Step

Recommend a decision on whether and how resources should, or should not, be committed to the portfolio or project.

Responsible Party

Local project appraisal committee, reported by QA Assessor

Template/Guideline
Explanatory Notes

Decisions include:
• Approve
• Approve with modifications
• Disapprove

1.2

Step

Review portfolio or project QA Assessment, make adjustments as needed and approve.

Responsible Party
Template/Guideline
Explanatory Notes

2.0

Step

Conduct implementation stage portfolio or project QA Assessment every two years, including identifying management actions to address any areas that need improvement.

Responsible Party
Template/Guideline
Explanatory Notes

Select Unit, Year, Portfolio or Project, Project No and Name, and “Create New Implementation and Monitoring Form”
 

2.1

Step

Review portfolio or project QA Assessment, make adjustments as needed and approve.

Responsible Party
Template/Guideline
Explanatory Notes

The QA Approver may consult others as appropriate.

2.2

Step

Determine one of three possible decisions for the project and take action accordingly.

Responsible Party

Programme Manager

Template/Guideline
Explanatory Notes

Decisions include:
• Continue
• Suspension
• Cancellation

3.0

Step

Conduct closure stage portfolio or project QA Assessment, and add summary comments and lessons learned as needed.

Responsible Party

QA Assessor

Template/Guideline
Explanatory Notes

Portfolio/Project QA - Closure User Guide (Quantum+)
 

3.1

Step

Review project QA Assessment, make adjustments as needed and approve. 

Responsible Party

QA Approver

Template/Guideline
Explanatory Notes

The QA Approver may consult others as appropriate.

Agreed Separation

1

Step

Submission of application.

 

Responsible Party

Staff Member, Country Office Management or OHR Business Partner

Template/Guideline
Explanatory Notes

If eligibility criteria are met, the staff member should submit application through Head of Office/Unit to which he/she is assigned.

2

Step

Review of application.

Responsible Party

OHR Business Partner

Template/Guideline
Explanatory Notes

Consider the interests of UNDP and takes into account whether criteria are fullfilled:

  • Review summary prepared by OHR on staff members applying for agreed termination;
  • Determine in the case of recommendations for approval, the applicable terms and conditions as outlined in policy;
  • Ensure process followed took place in full and fair consideration of the staff member's applications;
  • Ensures staff members being selected meet the criteria of the current agreed termination agreements;
  • Seek any additional information from relevant Bureau/Units or Offices
  • Seek Bureau Endorsement
  • Make recommendation to the Assistant Administrator and Director of BMS.

3

Step

Authorize payment of additional termination indemnities.

Responsible Party

Director, OHR

Template/Guideline
Explanatory Notes

Authorizes payment of additional termination indemnities, in accordance with, and limited to the amounts included in the schedule provided in Annex I.

 

4

Step

Decision to terminate the appointment. 

 

Responsible Party

Assistant Administrator and Director, BMS

Template/Guideline
Explanatory Notes

Approves termination of appointment.

 

5

Step

Sign Certificate of No Contest (CNC)
 

Responsible Party

OHR Business Partner, Staff Member

Template/Guideline
Explanatory Notes

Prepare CNC.

Required to sign the Certificate of No Contest (CNC) within two weeks of receipt of notification of approval. 

If staff member does not respond within one month of the date of notification of approval or agreed termination, the proposed agreed termination will lapse, and UNDP will initiate termination of appointment as per the UN Staff Rules and Staff Regulations, Annex III for all approvals. 
 

6

Step

Implementation of approved cases. 
 

Responsible Party

OHR Business Partner,

Staff member

Template/Guideline
Explanatory Notes

For locally recruited staff, prepare Request for Personnel Action to Global Payroll Services. 

For International Professional & General Service staff based at Headquarters, prepare RPA to BES/GSSC 
 

Multiple Funding Lines for Positions

1

Step

Assess and budget annually support services required from UNDP HQ and country offices in each development project. 

Responsible Party

Country Office Project Manager

Template/Guideline
Explanatory Notes

2

Step

Conduct the workload studies for the office 

Responsible Party

Template/Guideline
Explanatory Notes

WLS template​

3

Step

Include the direct project costs in programme project budgets

Responsible Party

Country Office Project Manager

Template/Guideline
Explanatory Notes

Project document. WLS results.

4

Step

Update the chartfield distribution of positions in Quantum HCM and position type in Quantum

Responsible Party

Country Office/Position Administrator

Template/Guideline
Explanatory Notes

Based on WLS results
 

Guidance for Quantum will be available soon
 

 

5

Step

Create speed charts for staff entitlement expenses that are paid directly through Quantum Payables module (not paid  through payroll HCM)

Responsible Party

Country Office Finance unit

Template/Guideline
Explanatory Notes

Based on WLS results

6

Step

Create speed charts for GOE (post-incumbency expenses such as rent, utilities, communications, supplies) in Quantum Payables module

Responsible Party

Country Office Finance unit

Template/Guideline
Explanatory Notes

Based on WLS results

7

Step

Revise position chartfield distribution if significant changes occur in service delivery

Revise development project budget to reflect the estimated position costs

Responsible Party

Template/Guideline
Explanatory Notes

Total number of positions that are co-funded from management and development funds are reported in DPC implementation report with respective proforma.

Procurement and Inventory Management and Reporting

1

Step

Manage inventory of consumables and equipment.

Responsible Party
Template/Guideline
Explanatory Notes

Stock should be used on the basis of a first-in/first-out policy.

All information relating to the physical inventory of non-expendable equipment covered by the UN Clinic should be reported in Atlas under a separate heading called ‘Medical Equipment'.

2

Step

Donate consumable stock if applicable.

Responsible Party
Template/Guideline
Explanatory Notes

Medications within the last month before expiry may be donated, after approval of the UN Medical Director, to local health facilities for immediate use.  This donation is subject to UNDP rules and procedures and a record kept for audit purposes.

3

Step

Prepare inventory report for UNCT on a quarterly basis

Responsible Party

Template/Guideline
Explanatory Notes

A detailed inventory of all consumables and non-consumables must be prepared before placing the yearly order.

4

Step

Prepare procurement orders promptly when stock is being reviewed or as needed.

Responsible Party

,

UN Medical Services ( DHMOSH)

Template/Guideline
Explanatory Notes

Procurement of medical goods and supplies should be based on the United Nations Clinic Catalogue of Fleischhacker accessible through UNMSD.

Purchasing should be standardized as far as possible and done through bulk orders.  Genuinely unforeseen requirements, including supplies for new UN Clinics and items that cannot be stocked for long periods, can be requested from the vendor with the approval of the UN Medical Director on an ad hoc basis or can be procured locally, subject to UNDP rules and procedures.

5

Step

Clear procurement list.

Responsible Party

Template/Guideline
Explanatory Notes

Clearance must be based on the full epidemiological profile of the duty station.

Responsible Party: WHO Representative as Chair of the LIACMC

6

Step

Obtain agreement of UNCT on recommended procurement list.

Responsible Party

Resident Representative

Template/Guideline
Explanatory Notes

7

Step

Approve procurement list.

Responsible Party

Resident Representative

Template/Guideline
Explanatory Notes

8

Step

Procure medical goods and supplies for UN Clinics against the Common Services project.

Responsible Party

CO

Template/Guideline
Explanatory Notes

Medical goods and supplies should be procured from one or a combination of the following sources:

1.  Reputable and approved local, regional, or international vendors, using use the existing LTA with UNDP;

2.  UNICEF where a local office exists in the same location;

3.  World Health Organization (WHO).

9

Step

Ensure funding is available for procurement, operation and  subsequent maintenance of non-medical equipment.

Responsible Party

CO

Template/Guideline
Explanatory Notes

10

Step

Procure non-medical equipment as needed.

Responsible Party

CO

Template/Guideline
Explanatory Notes

The UNDP Country Office directly procures non-medical equipment e.g. furniture, refrigerators, fans and any other non-medical items) subject to audit and accountability, rules, and procedures.

11

Step

Make payment for goods and services according to terms and conditions of procurement.

Responsible Party

CO

Template/Guideline
Explanatory Notes

Payments must be made with one of the following options:

1.  Bank transfers (most preferred option);

2.  Checks (least desirable option); or

3.  Agency Service Clearing Account via GLJE.

In either case, the following must be carefully observed:

1.  Bank Transfer: The UNDP Country Office must include all the banking details as provided on the invoice.

2.  Agency Service Clearing Account: The description field of the GLJE must refer to the invoice number indicated on the invoice and/or any other reference number.

3.  The GLJE must use the following chart fields: GL Account – 54015; Fund – 12000; and Donor – 00006.

12

Step

Prepare inventory control report(s).

Responsible Party

,

CO

Template/Guideline
Explanatory Notes