1.0
|
Step
Track performance: Collect progress data against indicator targets (IRRF, programme, project, as relevant), stakeholder feedback, evidence on contextual changes, and operational performance data against financial and efficiency targets, in the frequency stated.
|
Responsible Party
UNDP Programme Officer,
Project Manager,
Monitoring and Evaluation Officer
|
Template/Guideline
|
Explanatory Notes
Ensure that critical project information is monitored and updated in corporate systems. UNSDG Guidance Note on Big Data Security and Ethics Commitments to funding partners/donors should be part of regular monitoring
|
2.0
|
Step
Analyse evidence: Compare and analyse evidence against defined programming and operational baselines, milestones, targets and the theory of change, and identify factors related to progress, at least annually.
|
Responsible Party
,
Project Manager,
Monitoring and Evaluation Officer
|
Template/Guideline
|
Explanatory Notes
|
2.1
|
Step
Verify output progress and/or completion at least annually.
|
Responsible Party
UNDP Programme Officer,
Project Manager,
Monitoring and Evaluation Officer
|
Template/Guideline
|
Explanatory Notes
HACT guidelines require conducting programme monitoring as part of HACT assurance activities to verify output progress.
|
2.2
|
Step
Review transition arrangements, national ownership and sustainability plan, at least annually.
|
Responsible Party
Project Manager
|
Template/Guideline
|
Explanatory Notes
|
2.3
|
Step
Assess quality at least every other year.
|
Responsible Party
UNDP Programme Officer,
Monitoring and Evaluation Officer
|
Template/Guideline
|
Explanatory Notes
Project QA - Implementation and Monitoring User Guide (Quantum+)
|
2.4
|
Step
Assess risks and implementation of risk management measures, at least annually.
|
Responsible Party
,
Project Manager
|
Template/Guideline
|
Explanatory Notes
See Social and Environmental Standards See Enterprise Risk Management Policy
|
2.5
|
Step
Monitor operational performance.
|
Responsible Party
,
UNDP Programme Officer,
Project Manager
|
Template/Guideline
|
Explanatory Notes
|
2.6
|
Step
Review partnerships and communication strategy with pipeline and resource mobilization action plan, at least annually.
|
Responsible Party
,
Resident Representative
|
Template/Guideline
|
Explanatory Notes
|
3.0
|
Step
Inform decision-making to adjust the programme and project based on evidence and analysis from monitoring.
|
Responsible Party
,
Project Manager,
Programme Board,
|
Template/Guideline
|
Explanatory Notes
|
4.0
|
Step
Document lessons learned through existing reporting and assurance mechanisms.
|
Responsible Party
,
Resident Representative,
Project Manager
|
Template/Guideline
|
Explanatory Notes
Recording lessons learned takes place in the project space in the corporate planning system.
|