1.0 |
StepPrepare the annual report of the Administrator on the Strategic Plan. |
Responsible Party |
Template/Guideline |
Explanatory NotesConsider using the RBM Guidance to improve the ROAR Responses. |
2.0 |
StepSubmit Financial Report. |
Responsible PartyProject Manager |
Template/Guideline |
Explanatory NotesSee Appendix VI of UNSDG HACT Framework for the template of the FACE form and Appendix VII for guidelines for completing FACE form. Frequency: quarterly or when additional resources are needed. |
3.0 |
StepSign the Combined Delivery Report. |
Responsible PartyProgramme Manager/ Resident Representative Implementing Partner certifies |
Template/Guideline |
Explanatory NotesFrequency: second, third and fourth quarters Standard combined delivery report under construction in Quantum
|
4.0 |
StepPrepare a Quality Project Report. |
Responsible PartyProject Manager |
Template/Guideline |
Explanatory NotesFrequency: As stated in the project document. The standard project progress report in the Executive Snapshot is the standard report required by UNDP. Donors often require additional information beyond what is available in the standard report, so an optional template is provided as a resource. Some funding partners have specific reporting formats, such as the GEF and GCF. The GEF Annual Project Implementation Report (PIR) is completed online using the BPPS Nature, Climate and Energy PIMS+ system. The GCF Annual Performance Report (APR) is completed online using the BPPS Nature, Climate and Energy PIMS+ system.
|
5.0 |
StepDocument and communicate results to donors and other stakeholders, ensuring due credit is given to partners. |
Responsible PartyProgramme manager/Resident Representative,Programme officer |
Template/Guideline |
Explanatory Notes |