1.0 |
StepConduct Social and Environmental Screening to identify potential social and environmental risks, including dispute risks. |
Responsible PartyProject Developer and/or Portfolio Developer |
Template/Guideline |
Explanatory NotesGuidance Note: UNDP Social and Environmental Standards (SES) Stakeholder Response Mechanism (SRM) Guidance |
2.0 |
StepImplement identified management actions and track in Project Risk Register. |
Responsible PartyProject Manager |
Template/Guideline |
Explanatory NotesStakeholder Response Mechanism (SRM) Guidance Assess ongoing compliance with the Social and Environmental Standards as part of ongoing quality assurance and risk reporting.
Update SESP and risk categorization if there is a substantive revision to the project or if the context has changed in a way that alters the risk profile of the project. |
3.0 |
StepReview social and environmental and risk prevention and management experience; note lessons learned and opportunities for improvement in project closure/evaluation. |
Responsible PartyProject Manager |
Template/Guideline |
Explanatory Notes
|