1.0 |
StepMake funds available to the project/portfolio. |
Responsible PartyUNDP Programme Officer |
Template/Guideline |
Explanatory NotesRefer to Financial Management and Implementation Modalities on the provision of financial resources. Progress/financial reports will form the basis for continued funds availability. |
2.0 |
StepMobilize inputs to initiate activities and deliver outputs. |
Responsible PartyProject Manager, Portfolio Manager |
Template/GuidelineWhen UNDP carries out procurement, the online Quantum system should be used. See Use of Online Quantum System policy and procedures in the POPP Online Quantum System |
Explanatory NotesSee the Financial Management and Implementation Modalities. For detailed procedures related to input mobilization for a directly implemented project, see Procurement and Human Resources Management in the Programme and Operations Policies and Procedures. |
3.0 |
StepPerform oversight functions through periodic on-site spot checks, and scheduled audits included in the assurance activity plan. |
Responsible PartyUNDP Programme Officer, Third-party service provider |
Template/GuidelineTORs for periodic spot-checks: see Appendix IX and X, UNSDG HACT Framework Specimen Terms of Reference for NGO/NIM/HACT Financial Audits OAI Portal: NGO/NIM/HACT Financial Audits Evaluation Managers Roles and Responsibilities Monitoring and evaluation focal points roles and responsibilities Charter of the Office of Audit and Investigations RACI (Responsible, Accountable, Consulted and Informed) Matrix for GEF Projects Oversight |
Explanatory NotesHarmonized Approach to Cash Transfers (HACT) The Office of Audit and Investigations conducts audits in alignment with the International Standards for the Professional Practice of Internal Auditing, as issued by the Institute of Internal Auditors. The HACT, NIM and NGO audit terms of reference require auditors to follow either ISA or INTOSAI auditing standards. The RACI (Responsible, Accountable, Consulted and Informed) Matrix for GEF Projects Oversight details the oversight roles and accountability for GEF-funded projects. *See HACT policy for clearance by Bureaus for staff to carry out spot checks.
|
4.0 |
StepUpdate the multi-year workplan. |
Responsible PartyProject Manager, Portfolio Manager |
Template/Guideline |
Explanatory Notes
|