1 |
StepsReview preliminary Combined Delivery Report in the CDR Bridge Platform or in Atlas.
|
Responsible Party
|
Template/Guideline |
Explanatory NotesAtlas CDR Navigation: Main Menu > UN Reports > Project Management Reports > Portfolio Analysis > Combined Delivery Report
|
2 |
StepsQuarterly/year-end closure of ATLAS general ledger and submodules automatically triggers creation of CDRs in the CDR Bridge Platform. |
Responsible PartyOFM Chief of Accounts |
Template/Guideline |
Explanatory NotesQuarterly closure of the general ledger and submodules is communicated via email by OFM Accounts Unit. CDR Bridge platform |
3 |
StepsGrants access to UNDP programme staff authorized to approve CDRs in the CDR Bridge platform |
Responsible PartyRR/DRR/Operations Manager |
Template/Guideline |
Explanatory NotesRR/DRRs/OMs have rights in the CDR Bridge platform to grant access to staff in their office.
|
4 |
StepsRegister Implementing Partners certifying official to individual Atlas Awards in the CDR Bridge Platform |
Responsible Party
|
Template/Guideline |
Explanatory NotesProgramme staff enters the email of the Implementing Partners certifying official against individual Atlas Awards in the CDR Bridge Platform. CDR Bridge platform |
5 |
StepsConfirm CDR Report by Atlas Award is complete and accurate in the CDR Bridge Platform. |
Responsible Party
|
Template/Guideline |
Explanatory NotesThe confirmation triggers an email to be sent to the implementing partner registered against the Atlas Award with a cover letter requesting the implementing partner to certify the CDR within 15 calendar days from the date the request is sent. |
6 |
StepsCertify CDR report in the CDR Bridge Platform |
Responsible PartyImplementing Partner Certifying Official |
Template/Guideline |
Explanatory NotesThe CDR is certified (or rejected) by the implementing partner authorized official in the CDR Bridge platform. If CDR is rejected, the implementing partner enters comments in the CDR Bridge Platform explaining the rejection. |
7 |
StepsCDR Bridge platform sends an automated follow-up request to the implementing partner if no response is received within 15 calendar days of the initial request. |
Responsible PartyCDR Bridge Platform |
Template/Guideline |
Explanatory NotesThe follow-up request states that the CDR shall be deemed to have been accepted if no response is received within 15 calendar days from the date the follow-up request.
|
8 |
StepsReceipt of certified CDR |
Responsible Party
|
Template/Guideline |
Explanatory NotesIf the CDR is certified in the CDR Bridge Platform by the implementing partner, the CDR is flagged green.
If a manual copy of the certified CDR was mailed back by the partner, it needs to be scanned and uploaded into the CDR Bridge Platform. UNDP Programme staff should follow-up on rejected CDRs and take appropriate actions. |
9 |
StepsThe Q4 certified CDR is required by auditors as the basis for auditing expenses of nationally implemented projects. |
Responsible PartyAuditor firms (service providers) |
Template/Guideline |
Explanatory NotesOAI requires audit firms (service providers) who carry out HACT financial audits or DIM audits to include in their audit reports a copy of the signed CDR for Q4. Therefore, at year-end, offices should ensure all Q4 CDRs are certified. |