1 |
StepDevelop Procurement Risk Assessment (PRA), based on project concept note Keep as a risk log to be regularly monitored and updated |
Responsible PartyHead of Programme and Operations Manager |
Template/Guideline |
Explanatory NotesEnsure both Programme and Operations are aware of procurement challenges |
2 |
StepApprove a procurement plan |
Responsible Party
|
Template/Guideline |
Explanatory NotesProcurement plans are required for “standard or complex business needs”, a Head of BU has to approve all procurement plans by monitoring requisite report in QUANTUM. All procurement plans (Project and Operations) are established at the activity level in projects in Quantum. Consolidated plans can be viewed and analyzed in Quantum by running the applicable reports. |
3 |
StepCategorize the project as having “Complex Business Needs” |
Responsible PartyBusiness Unit Head |
Template/Guideline |
Explanatory NotesProjects with "Complex Business Needs" are defined as being those that meet one or more of the following conditions:
i. Drugs & Pharmaceuticals ii. Security Services iii. Laboratory Equipment & Medical Supplies iv. Medical kits (when specialized) v. Contraceptives vi. Elections Equipment vii. Consultancy Firm Services viii. Permanent Structures ix. Construction Services x. Technical Studies (when they are highly specialized and could impact downstream work).
|
4 |
StepInform PSU of project details |
Responsible PartyBusiness Unit Head |
Template/Guideline |
Explanatory NotesProjects categorized as having Complex Business Needs require more rigorous procurement planning. In some instances it may be advisable for the Business Unit to contact the Office of Pocurement (OP) to obtain necessary assistance. |
5 |
StepProvide guidance to BU |
Responsible PartyOffice of Procurement/Bureau for Management Services |
Template/Guideline |
Explanatory Notes |
6 |
StepDevelop a detailed risk mitigation plan for all individual projects in this category using the Risk Assessment Matrix. |
Responsible PartyProgramme Manager, Operations Manager |
Template/GuidelineThe risk assessment matrix is a tool, developed alongside the policies and the procedures that will allow the risks of a specific project to be identified. The template will be linked to the POPP screen for the initial rollout. |
Explanatory NotesIn particular the matrix has been designed to highlight: |
7 |
StepEnsure the implementation of mitigation plans. |
Responsible PartyBusiness Unit Head |
Template/Guideline |
Explanatory Notes |
8 |
StepPrepare a Procurement Plan using corporate web-based planning tool. |
Responsible PartyProgramme/DRR/Operations Manager/ Head of Procurement |
Template/Guideline |
Explanatory NotesIn particular, Programmes should define key procurement requirements, while Operations should determine appropriate procurement methods.
|
9 |
StepReview Procurement Risk Matrix and Procurement Plan |
Responsible PartyBusiness Unit Head |
Template/Guideline |
Explanatory Notes |
10 |
StepBased on CO needs, provide guidance to the CO |
Responsible PartyOffice of Procurement/Bureau for Management Services |
Template/Guideline |
Explanatory Notes |
11 |
StepApprove project for submission to Commitment Control (if necessary steps have been taken to comply with policy and procurement needs have been satisfactorily addressed). |
Responsible PartyHead of BU |
Template/Guideline |
Explanatory NotesUse Finance Module of Quantum. |
12 |
StepEnsure that the BU’s “Consolidated Procurement Plan” shall be updated whenever new projects are approved, and/or when the procurement plans for already approved projects are modified. |
Responsible PartyDRR/OM/Head of Procurement |
Template/Guideline |
Explanatory NotesThe online tool provides real time access and updates. |
13 |
StepHold programme / operations joint meetings on a regular basis as appropriate to monitor risks by going through questions of the Procurement Risk Assessment |
Responsible PartyHead of BU |
Template/Guideline |
Explanatory NotesFor high-risk procurement |
14 |
StepContact the Office of Procurement for advice and guidance |
Responsible PartyHead of BU |
Template/Guideline |
Explanatory NotesBUs are encouraged to inform the Office of Procurement when projects are categorized as “Complex Business Needs.” |
15 |
StepProvide tailored support |
Responsible PartyPSU/BMS |
Template/Guideline |
Explanatory Notes |
16 |
StepReview of Procurement Forecasting and Delivery for all projects categorized as “Complex Business Needs”. |
Responsible PartyHead of Programme and Operations Manager |
Template/Guideline |
Explanatory NotesOffice of Procurement /Bureau for Management Services codify case studies to enhance knowledge management on righ-risk and/or high volume procurement. |