Search
Policy Areas

Programme Suspension

1.0

Step
The Regional Bureau, in collaboration with the country office, prepares a note that the Administrator submits to the Executive Board giving reasons for requesting suspension of the programme, and proposes management arrangements for continued assistance to the country.
Responsible Party

Regional Bureau Director

Template/Guideline
Explanatory Notes

The note should also explain the implications for harmonized programme periods, and the related consultations that have taken place within the UN country team (including, for example, a programme criticality assessment). In the note, the Administrator may seek authority from the Executive Board to approve assistance on a project-by-project basis until the situation permits a return to normal operations.

Programme suspension note forthcoming.

2.0

Step
The Regional Bureau presents the note to the Associate Administrator through the BPPS Effectiveness  Group for review and clearance for submission to the Executive Board for approval.
Responsible Party

Regional Bureau Director

Template/Guideline
Explanatory Notes

Micro Assessment

1

Step

Determine and prioritize which Partner require micro assessment.

Responsible Party

Office

Template/Guideline
Explanatory Notes

Micro Assessment should be carried out before programme funding is provided. Where two or more programmes have similar start dates, prioritization should be based on the assessed relative amount of risk to UNDP (funding quantum, and past experience with the Partner)​.

2

Step

Develop micro assessment plan.

Responsible Party

Office

Template/Guideline
Explanatory Notes

Final Micro Assessment Plan must be signed off by the Head of Office or his/her designate.
The relevant planning process should be completed in the HACT platform.
 

3

Step

Solicit third party service provider.

Responsible Party

Office

Template/Guideline
Explanatory Notes

UNDP office should consider Long Term Arrangements with one or more service providers for micro assessments. Global LTAs for service providers are available at HACT Long Term Agreements (LTAs). 

See TOR of service provider for the micro assessment​. 

4

Step

Perform micro assessment.

Responsible Party

Service Provider

Template/Guideline
Explanatory Notes

Key output are: 

(1) An overall risk rating related to cash transfers to Partner.
(2) Significant issues of Partners ​

5

Step

Review results of micro assessment.

Responsible Party

Office

Template/Guideline
Explanatory Notes

Results of micro assessment shall be reviewed by Head of Office or his/her designate and remedial actions shall be discussed with the Partner. 

The micro assessment report should be uploaded in the HACT Platform. Issues highlighted in the report including the action plan needs to be documented in the HACT Platform.  

6

Step

Establish impacts and implications on AWP design.

Responsible Party

Office

Template/Guideline
Explanatory Notes

Office to assess the impact of the micro assessment and implications on AWP design

7

Step

Identify requirement for HACT assurance planning.

Responsible Party

Office

Template/Guideline
Explanatory Notes

Office to assess the impact of the micro assessment and implications on HACT assurance plan. 

8

Step

Document Partner risks as appropriate.

Responsible Party

Office

Template/Guideline
Explanatory Notes

The specific risks identified in the micro assessment are also incorporated into country level risk management activities and logs, as appropriate.

Receipt of Goods, Services and Works

1

Step

Raise PO to acquire the goods, services and works.

Responsible Party
Template/Guideline
Explanatory Notes

For non-PO invoice, offices are not required to enter a receipt date in Quantum, however, the offices are required to make sure the payment are processed in the correct accounting period.

2

Step

Deliver goods, render services and perform the works.
 

Responsible Party

Supplier

Template/Guideline
Explanatory Notes

Shipment of the goods according to the contract and INCOTERMS 2020. Render the services and perform the works according to the contract.

Ensure all the relevant supporting documents are provided to the buyer.

Liaise with the Buyer on contract management issues (if delivery is not according to the procurement contract).

3

Step

Delivery of goods.
 

Responsible Party

Shipment Carrier (If applicable)

Template/Guideline
Explanatory Notes

Physical delivery of the goods to the specified location.

4

Step

Certify the receipt of the shipment and inspect goods.

Responsible Party

Shipment Carrier (If applicable)

Template/Guideline
Explanatory Notes

Certify the receipt of the shipment. Proceed with the delivery to UNDP and forward the supporting documentation such as delivery note, bill of landing, shipping bills, insurance papers to UNDP.
 

5

Step

Physically receive the goods, services and works.

Responsible Party
Template/Guideline
Explanatory Notes

Buyers exercise their procurement role on behalf of Project Managers and other clients. To achieve segregation of duties, the Buyer must not perform the receipts of goods, services or works in the Quantum.

6

Step

Review supporting documentation.

Responsible Party
Template/Guideline
Explanatory Notes

Review supporting documentation such as GRN, shipping documents, custom clearance, insurance etc. Follow up with both the Supplier and Shipment Carrier if necessary.

7

Step

Notify requester, project manager and finance.

Responsible Party
Template/Guideline
Explanatory Notes

Notify the requester/project manager about the shipment, so that the requester knows when to expect the physical receipt of the goods.
Forward the invoice and payment information to finance unit for payment to the Supplier.

8

Step

Enter a receipt in Quantum to record event when goods and services are received by UNDP in accordance with the terms and condition set out in the contract or PO. 

Responsible Party

Project Manager

Template/Guideline
Explanatory Notes

Managers may delegate this function to other project staff. Where the volumes are significant, this delegation should be in writing and should be copied to the Operations Manager, so that the Finance unit is aware of the delegation.

The office has two options for receipting in Quantum:

  • The Project Managers (or his/her designate) documents receipt on the Goods Received Note (GRN), and forwards the GRN to the Finance unit to record, in Quantum, receipt of goods, services or works.
  • Project Manager (or designate) directly record receipt of goods, services and works in Quantum after verifying.

It is important that the receipts be entered promptly in Quantum when the goods and services are actually received. It is mandatory to enter receipts in Quantum within 48 hours of actual receipt of goods and services, so that the expense and asset recognition is done correctly in accordance with UNDP accounting policy.

When UNDP procures "services", receipts must be entered in Quantum on the date when services are a properly rendered according to the contract and accepted. For services such as individual contracts (IC), it is important to enter receipts when actual deliverables are achieved against milestones, if any, defined in the contract, e.g. submission of reports, assessments, certain number of hours etc. If the contract runs for a longer period of time, but several deliverables or payments are agreed upon, then receipts occur at each deliverable. For instance, for a six-month IC with monthly payments for which a PO has been raised, a portion equivalent to the monthly payment needs to be received each month before the payment of the IC. 

Prompt receipt of goods in Quantum also determines when to capitalize an item (for capital assets) and also facilitates evaluation of supplier performances. 

Careful attention to Incoterms under which goods are being procured is required, as this will also dictate the date when the receipts are to be entered in Quantum. For example, if the goods are being procured under FOB-shipping point basis, then the risk of losses during the shipping is transferred to UNDP as soon as the supplier hands over the goods to the shipper. Thus, the "receipt date" on which the goods are deemed to be received by UNDP will be the date when goods were handed over to the shipper. A receipt must be entered in Quantum immediately even though the actual goods have not arrived at the destination. However, a physical verification of such goods on actual arrival must be carried out, recorded and supporting documents uploaded to the Quantum procurement receipt application. 

Construction works (collectively, "Works") need to be received/recorded at the stage when milestones, according to the contract, are completed and accepted by the UNDP as part of the regular project monitoring activities.

Refer to the policy in regard to the receipt date for different Incoterm.

INCOTERMS 2020

International Commercial Terms

9

Step

Create partial receipts in Quantum.

Responsible Party

Project Manager

Template/Guideline
Explanatory Notes

Partial receipts can be created in Quantum when the goods and services are being delivered progressively rather than all at once.

10

Step

Forward the receipt and shipping information to the Buyer for reference if everything is in order.

Responsible Party
Template/Guideline
Explanatory Notes

If the inspection shows any reason for complaint, the contract management sub-process is activated (liaison with Buyer, Supplier, shipment carrier and insurance company, as required).

Revenue Process Procedures

1

Step
Sign Contribution Agreements

Responsible Party

Head of Office

Template/Guideline
Explanatory Notes

2

Step
Entry into UNITY/ UNALL within 1 week of signature
Responsible Party

UNDP office staff assigned by the head of office/unit

Template/Guideline
Explanatory Notes

3

Step
  
Entry into the Contract Management Module and activate contract. Contract Information to be entered
Responsible Party

Revenue Specialist (GSSC Finance Function)

Template/Guideline
Explanatory Notes

3.1

Step
Overview – Includes all the general information relating to the agreement
Responsible Party

Revenue Specialist (GSSC Finance Function)

Template/Guideline
Explanatory Notes

3.2

Step
Accounting Distribution - This is the full chart of account information relating to the revenue and accounts receivable provided by the UNDP Office to GSSC
Responsible Party

Revenue Specialist (GSSC Finance Function)

Template/Guideline
Explanatory Notes

3.3

Step
Agreement date - This is the date that the agreement came into effect and is the key trigger that is set-up in the Contract Management Module for revenue recognition. These are dependent on type of agreements and interpretation of relevant IPSAS policy.
Responsible Party

Revenue Specialist (GSSC Finance Function)

Template/Guideline
Explanatory Notes

3.4

Step
Invoice event - The invoice event includes the event type that needs to be achieved to create the billing and generate Accounts Receivable entries in the General Ledger
Responsible Party

Revenue Specialist (GSSC Finance Function)

Template/Guideline
Explanatory Notes


3.5

Step
Revenue Event - The revenue event will be created upon signing the relevant contribution agreement as revenue entries are generated upon signature of the contribution agreement.
Responsible Party

Revenue Specialist (GSSC Finance Function)

Template/Guideline
Explanatory Notes

3.6

Step
Amendments - Amendments can be made to original contracts that have already been entered in the Contract Management Module using the amend function
Responsible Party

Template/Guideline
Explanatory Notes

4

Step
Review contract in Contract Management Module

Responsible Party

GSSC Manager (GSSC Approving Manager)

Template/Guideline
Explanatory Notes

5

Step
Record the receipt of contributions against the accounts receivable item, provided that the following documents are available:
- Notification of receipt into UNDP bank account from the bank; or
- Receipt of a cheque.




Responsible Party

GSSC Treasury & GSSC Deposits (GSSC Finance Function)

Template/Guideline
Explanatory Notes

6

Step
Application of funds
Responsible Party

Template/Guideline
Explanatory Notes

7

Step
Approval of invoice adjustment (Note: In Quantum, approval of application of fund is not required)
Responsible Party

GSSC Manager (GSSC Approving Manager)

Template/Guideline
Explanatory Notes

8

Step
Monitor Unapplied receipts
Responsible Party
Template/Guideline
Explanatory Notes

9

Step
Review and follow-up of accounts receivable    
Responsible Party

First authority (Project Manager)

Template/Guideline
Explanatory Notes

10

Step
Sign off as evidence of review of accounts receivable
Responsible Party

Approving Manager or Program Manager

Template/Guideline
Explanatory Notes

11

Step
Recommend write-off or doubtful debts provision with the appropriate justification 
Responsible Party

Head of Office

Template/Guideline
Explanatory Notes

12

Step
Approve provision for write-off
(This role is not included in the ICF but included in this table as it is considered a necessary step.) 

Responsible Party

Chief of FPMR/OFM

Template/Guideline
Explanatory Notes

13

Step
Approve write-off   
Responsible Party

Template/Guideline
Explanatory Notes

Provision or Impairment of Financial Assets and Accounting for Fraud and Financial Loss

1

Step
Provision or Impairment of Financial Assets and Accounting for Fraud and Financial Loss
Responsible Party
Template/Guideline
Explanatory Notes

The Standard Operating Procedure document provides the procedures to be applied for the recognition of an allowance for doubtful accounts, as well as the treatment of losses due to fraud and financial loss. The procedure contains two sections:

  • The first section provides the process and procedure for determining an allowance/impairment for financial assets in the UNDP accounts.
  • The second section depicts the accounting procedures related to losses due to fraud and financial loss. 

Organized Shipments

1.a)

Step

Shipping Arrangements: (These do not apply to staff that have opted for the Relocation Grant): a) if shipping from NY or from a place where there is no UNDP office, contact the TSS once the shipment has been authorized, to discuss the forwarding arrangements.
 

Responsible Party

Staff Administrative Services (BES/JPOSC)

Template/Guideline
Explanatory Notes

The SM must clearly indicate to the estimator and to the packers which items he/she intends to ship and whether the goods will be shipped by air or by surface;
 

1.b)

Step

An estimate of the goods that the staff member intends to ship must be arranged with the forwarding agent/agents as early as possible and the list of the items included in the estimate must be signed by both the SM or his/her representative, and the forwarding company; 
 

Responsible Party

Staff member

Template/Guideline
Explanatory Notes

An estimate of the goods that the staff member intends to ship must be arranged with the forwarding agent/agents as early as possible and the list of the items included in the estimate must be signed by both the SM or his/her representative, and the forwarding company; 
 

1.c)

Step

If shipping from a place where there is a UNDP office, contact the local HR/Operations Manager, once the shipment has been authorized, to make the shipping arrangements using an authorized forwarding agent.
 

Responsible Party

Staff member

Template/Guideline
Explanatory Notes

The SM or his/her representative must be present at the time of packing to ensure that the packing list accurately describes the goods and their condition. He/she should sign the packing list, noting any exceptions if necessary, and retain a copy of the list which will be helpful in preparing an insurance request, or filing an insurance claim.
 

1.d)

Step

If the shipment is estimated to exceed the weight entitlement, the shipping company will advise the SM. If the SM agrees to the charges assessed by the shipping company they will need to arrange proper payment directly with the shipping company.
 

Responsible Party
Template/Guideline
Explanatory Notes

2.a)

Step

For shipments arriving in the NY tri-state area, contact the Traffic Unit, UN Secretariat, Room FF-0285, tel. (212) 963-9389 (212) 963-9389 , email shipments@un.org

Immediately upon arrival in NY to provide them with the following documents required for customs clearance: copies of a) G-4 visa; b) I-94; c) passport; d) ocean bill of lading or airway bill; e) shipment arrival notice; and f) approved travel request .
 


 

Responsible Party

Staff member

Template/Guideline
Explanatory Notes

The SM (including SMs who have opted for the Relocation Grant) should be at the destination when the shipment arrives to attend to customs clearance requirements and delivery to residence. The SM will be liable for any charges resulting from delays attributed to his/her failure to do so.
 

2.b)

Step

For shipments arriving in the CO and other BUs outside of HQs, contact the local HR/Operations Manager to complete the customs clearance forms (this also applies to staff who have opted for the Relocation Grant) and to make arrangements for the clearance and delivery of the shipment.
 

Responsible Party

Staff member

Template/Guideline
Explanatory Notes

On taking delivery of the shipment, the SM (or the person authorized by the SM to receive the shipment) should take note of any external damage to the shipment, or any missing packages or crates.
 

3.a)

Step

Contact the SM if contact information has been provided ; arrange for the estimate, packing and pick-up of the shipment in accordance with both the SM’s written instructions and the authorized entitlement (weight, , origin and destination, mode of shipment and the number of shipments.
 

Responsible Party
Template/Guideline
Explanatory Notes

The CO and other BUs outside of HQs will arrange for at least three forwarding companies to view and estimate the weight of the goods and to provide their quotations; evaluate the quotations on the basis of cost and quality of service and award the job accordingly; endeavor to arrange shipments door-to-door and settle all costs with the forwarding agent; if necessary to arrange a shipment door-to-port, ensure that the destination services will be handled by the CO and other BUs outside of HQs at the destination, or by TSS/GO/BMS  if there is no UNDP CO at destination.
 

3.b)

Step

As soon as the shipment takes place, a) forward original shipping documents to the destination agent or the UNDP office handling the destination services ; b) provide the SM with a copy of all relevant shipping documents ; c) provide the UNDP office, or UNDP GO/TSS if there is no UNDP office at destination, with shipping details (departure/arrival dates, mode of shipment, shipping line,ocean bill of lading or airway bill number, weight of shipment, and number of pieces ; d) if shipment was arranged door-to-port, authorize the UNDP office at destination, or TSS/GO/BMS if there is no UNDP CO at destination, to arrange the destination services (clearance, storage - if authorized, and delivery to residence, providing such office with the relevant debit instructions (approved travel request number, PO number, chart of accounts-COA). 
 

Responsible Party
Template/Guideline
Explanatory Notes

4.a)

Step

Arrange for customs clearance as soon as possible in order to avoid demurrage charges.
 

Responsible Party
Template/Guideline
Explanatory Notes

In case of delays, the reason/s for such delays should be documented and the party/ies responsible for such delays identified for the purpose of pinpointing responsibility and accountability.
 

4.b)

Step

If the shipment was arranged : a) door-to-door, do not make any payment for destination services, unless specifically authorized by the office which arranged the shipment ; b) door-to-port, and the office which arranged the shipment has authorized the CO to arrange for destination services, settle the relevant invoice and charge the costs in accordance with the authorizing CO’s or with TSS/GO instructions, approved travel request, PO number and COA.
 

Responsible Party
Template/Guideline
Explanatory Notes

5.a)

Step

Relocation Grant (RLG): Indicate his/her preference in writing to the appropriate Human Resource (HR) Service Center.
 

Responsible Party
Template/Guideline
Explanatory Notes

The SM will be required to sign an attestation waiving the normal shipping entitlement for shipment and accepting the lump sum payment as complete for all costs related to his/her relocation. 
 

5.b)

Step

For moves administered by COs, pay RLG in the appropriate amounts upon notice from the HR Service Centre 
 

Responsible Party
Template/Guideline
Explanatory Notes

5.c)

Step

For moves administered by COs, pay RLG in the appropriate amounts upon notice from the HR Service Centre.
 

Responsible Party

Resident Representative

Template/Guideline
Explanatory Notes

6.a)

Step

Insurance arrangements: Submit a fully completed Itemized Valued Inventory form PT.78 (with a copy of the travel authorization indicating the insurance entitlement) to TSS/GO /BMS if making more than one shipment, an itemized valued inventory for each shipment must be prepared separately. 
 

Responsible Party

Staff Member (who has not opted for the RLG)

Template/Guideline
Explanatory Notes

If the total value of the inventory exceeds the insurance entitlement and the staff member has not indicated his/her agreement to pay for the over-entitlement, coverage will be requested only up to the maximum insurance entitlement.

The itemized valued inventory should list all articles in the shipment, including containers such as suitcases, and the replacement value in U.S. dollars of each article in the inventory. All articles of special value, such as antiques, jewelry, furs and coin and stamp collections, should be listed separately.

Information on the premium chargeable under the UN insurance policy is available upon request from the office that is responsible for arranging the insurance of the shipment
 


 

6.b)

Step

If the SM indicated on the PT.78 his/her agreement to pay for excess insurance coverage, inform him/her of the amount to be recovered from salary; if the SM is separating from service, collect the excess premium before submitting the PT.78 to UNTTS. 
 

Responsible Party
Template/Guideline
Explanatory Notes

6.c)

Step

Extension of insurance to cover personal effects/HHG placed in storage after shipment: Request an extension of coverage (from the arrival at the port to the date the goods are delivered to residence) from the company which insured the shipment so that the goods would be protected in the event of an insurance claim; request extension of insurance from the UNTTS (if insured through the UN) ; otherwise, request directly from the insurance company. 
 

Responsible Party

Staff member

Template/Guideline
Explanatory Notes

SM is advised to arrange extension of insurance with the same company that was used for the in-transit insurance to ensure continuity .

SM should provide name and location of the commercial warehouse, the date the goods were placed in storage.

Storage insurance ceases automatically upon expiration of the period for which the SM has paid the premium for storage insurance.
 


 

7. a)

Step

Insurance Claim (This does not apply to staff who have opted for the Relocation Grant): Write a memorandum or letter addressed to the Chief of Transportation Operations Unit, UNTSS, Room FF-0279 Mr. Guido den Braven, indicating origin/destination, mode, delivery date of shipment and listing the items damaged/missing with dollar amounts of claim. 
 

Responsible Party

Staff member

Template/Guideline
Explanatory Notes

A completed PT-78 (Itemized Valued Inventory/Request for Insurance Coverage) should have been submitted to UNTTS prior to on forwarding of shipment.

Make arrangements to have the shipment unpacked and examined immediately upon delivery;
 Make notations on the delivery receipt describing the nature and extent of the loss/damage in a quantifiable manner; do whatever is necessary to prevent further loss or damage; do not dispose of damaged property or packing material until a survey has been made; do not accept offers of settlement from carriers without the underwriter's approval; immediately contact the UN Transportation Operations Unit, Shipment Team at 
menonj@un.org, (tel.212-963-6287

212-963-6287);
 nwe@un.org, (tel.212-963-6202

212-963-6202);
 ganze@un.org, (tel.212-963-9389

212-963-9389);
 abalos@un.org,(tel.212-963-9388) for further instructions;

Keep a copy of all documents forwarded to UNTSS.
 


 

Framework of Accountability for Security

1

Step

Provide guidance to UNDP managers and personnel on key UNSMS/UNDP security responsibilities
 

Responsible Party

Programme and Project Managers UNDP, UNV, UNCDF,

Security Focal Point,

Resident Representative

Template/Guideline
Explanatory Notes

All to familiarize themselves with security responsibilities inherent to their respective roles.
 

UNDP-supported Guarantees Procedures

1

Step
Guarantee Origination:  CO identifies opportunity to use guarantee, conducts initial diagnostic, drafts concept note and initiates country risk assessment, consulting with the GPN and Guarantees Project Team as required, and submits proposal for review.
Responsible Party

CO in consultation with GPN & Guarantees Project Team

Template/Guideline
Explanatory Notes
Guarantees Project Team is a dedicated project team established to support the initial phases of roll out of the guarantees policy.

2

Step
Review guarantee proposal, including the diagnostic, evidence of positive impact and country risk assessment. Approve or request CO to revise and resubmit.
Responsible Party

Finance Sector Hub &GPN

Template/Guideline
Explanatory Notes

3

Step
Conducts financial and programmatic structuring of the guarantee, including appropriate exit strategy, pricing based on credit risk assessment of the lending portfolio and cost recovery, consulting with the Guarantees Project Team and GPN as required. Guarantees Project Team reviews the guarantee structure, including proposed pricing and cost recovery, and requests CO to modify if necessary
Responsible Party

Template/Guideline
Explanatory Notes

4

Step
Initiate identification, screening (including initial due diligence and credit risk assessment), selection and engaging of lender(s) and guarantee issuer in consultation with Guarantees Project Team and BMS/OFM Treasury.
Responsible Party

CO in consultation with Guarantees Project Team & BMS/OFM Treasury

Template/Guideline
Explanatory Notes

5

Step
Conduct solicitation process for guarantee issuer. Provide advice, review and clearance for lender(s) selection. Provide advice on due diligence and credit risk assessments, as required. Initiate formal agreement process with guarantee issuer.
Responsible Party

BMS/OFM Treasury

Template/Guideline
Explanatory Notes

6

Step
Conduct initial due diligence and credit risk assessment of lender(s) and guarantee issuer, consulting with Treasury as required. Assess if OK to proceed with guarantee. If not OK, reject guarantee proposal and notify CO.
Responsible Party

Guarantees Project Team

Template/Guideline
Explanatory Notes
Due diligence on borrowers is conducted by lender(s). 

7

Step
Modify financial and programmatic structuring, if necessary, in consultation with Guarantees Project Team and GPN, and submit guarantee documentation (agreements) for review. 
Responsible Party

Template/Guideline
Explanatory Notes

8

Step
Review guarantee arrangement, advise on legal and other issues/risks of the guarantee, and approve or reject the guarantee arrangement. For exceptional cases, Treasury escalates the guarantee to the Credit Risk Committee and CFO for review.
Responsible Party

Template/Guideline
Explanatory Notes
Refer to paragraph 49 for examples of cases that must be escalated to the Credit Risk Committee for review and approval.

9

Step
Credit Risk Committee and CFO review exceptional cases and approve/reject or escalate to Enterprise Risk Management (ERM) committee for final decision. 
Responsible Party

Credit Risk Committee & CFO, followed by ERM Committee

Template/Guideline
Explanatory Notes
Credit Risk Committee will be advised and supported by the Guarantees Project Team

10

Step
If guarantee agreement is cleared, record the guarantee and assign guarantee funds to the escrow account
Responsible Party

Treasury,

BMS/GSSU and BMS/OFM Treasury

Template/Guideline
Explanatory Notes

11

Step
Conduct ongoing programmatic and financial monitoring, reporting and oversight of guarantees.
Responsible Party

CO, GPN, Finance Sector Hub, Guarantees Project Team, BMS/OFM Treasury, Credit Risk Committee, ERM Committee

Template/Guideline
Explanatory Notes
Includes providing donor reporting and refunds where required by financing agreements.

Probation upon Appointment

1.0

Step

Assessment of performance during probation

Within three weeks after entry on duty: Discuss job description and confirm duties


 

Responsible Party

Staff member

Template/Guideline
Explanatory Notes

The first level supervisor discusses the job description with the staff member and provides them with a plan of work embracing the duties to be performed or objectives and tasks to be completed within six months after entry on duty;


Staff and supervisors will have to use the Word version of the Probationary Performance Appraisal Report while the PMD site is being updated.

 

1.1

Step

No later than six months after entry on duty: Complete staff member's Probationary Performance Appraisal Report

Responsible Party

Staff member

Template/Guideline
Explanatory Notes

The first level supervisor completes a Probationary Performance Appraisal Report, and discusses it with the staff member.
 

1.2

Step

No later than ten months after entry on duty: Second review for staff member's Probationary Performance Appraisal Report
 

Responsible Party

second level supervisor,

Staff member

Template/Guideline
Explanatory Notes

The first level supervisor completes the Probationary Performance Appraisal Report for the second review period and includes the second level supervisor’s decision to:
 

a) confirm the appointment;

b) extend the probationary period; or

c) not confirm the appointment. 
 


 

2.0

Step

Confirmation of appointment

 

Responsible Party

second level supervisor,

Staff member

Template/Guideline
Explanatory Notes

If the second level supervisor recommends confirmation of appointment, the report, including any attachments, is included in the staff member's personnel file. A copy is sent to the staff member.

 

3.0

Step

Extension of Probationary Period

 

Responsible Party

second level supervisor,

OHR

Template/Guideline
Explanatory Notes

If the second level supervisor decides that the extension of the probationary period is warranted, the Office of Human Resources is informed of the reasons for the extension. and is provided with a copy of the Probationary Performance Appraisal Report, together with any observations of the staff member. If the probationary period is extended:
 
a) The first within-grade salary increment is suspended for the staff member concerned and is granted retroactively to the staff member if the appointment is subsequently confirmed.


b) A further plan of work is established by the first level supervisor covering the period of extension. At the end of the extension, the Second level supervisor’s decides to: i) confirm the appointment; or 

c) not confirm the appointment. c)Copies of the report, notice of extension, work plan and other relevant documents are included in the staff member's personnel file.

 

4.0

Step

Termination of appointment
 

Responsible Party

second level supervisor,

BMS Director

Template/Guideline
Explanatory Notes

If the second level supervisor considers that separation is in UNDP’s interest because the probationary period was not satisfactorily completed, the staff member must be notified in writing.


The staff member has five working days following receipt of the written notice in which to comment. A copy of the staff member's comments is sent to the Office of  Human Resources, along with any supporting documentation.


After consideration of the staff member's reply or, failing such reply, at the close of the five-day period, the second level supervisor submits a recommendation to the Director, Human Resources, who forwards it to the Assistant Administrator and Director Bureau for Management Services (BMS) (for decision, with further comments as necessary.


The Director, Human Resources advises the second level supervisor concerned and the staff member of the decision taken. Copies of the report, the notification and other relevant documents are included in the staff member's personnel file.
 

Subscribe to